Tutorial

To start with businessdate import it. Note that, since we work with dates, datetime.date might be useful, too. But not required. Nevertheless datetime.date is used inside businessdate.businessdate.BusinessDate from time to time.

>>> from datetime import date, timedelta
>>> from businessdate import BusinessDate, BusinessPeriod, BusinessRange, BusinessSchedule

Creating Objects

BusinessDate

Once the library is loaded, creating business dates as simple as this.

>>> BusinessDate(year=2014, month=1, day=11)
BusinessDate(20140111)

>>> BusinessDate(date(2014,1,11))
BusinessDate(20140111)

>>> BusinessDate(20140111)
BusinessDate(20140111)

>>> BusinessDate('20140111')
BusinessDate(20140111)

>>> BusinessDate('2015-12-31')
BusinessDate(20151231)

>>> BusinessDate('31.12.2015')
BusinessDate(20151231)

>>> BusinessDate('12/31/2015')
BusinessDate(20151231)

>>> BusinessDate(42369) # number of days since January, 1st 1900
BusinessDate(20151231)

Even iterators like list or tuple work well.

>>> BusinessDate((20140216, 23011230, 19991111, 20200202))
(BusinessDate(20140216), BusinessDate(23011230), BusinessDate(19991111), BusinessDate(20200202))

Much easier to generate container with periodical items is using businessdate.businessrange.BusinessRange.

By default an empty businessdate.businessdate.BusinessDate is initiated with the system date as given by +datetime.date.today()*. To change this behavior: just set the classattribute businessdate.businessdate.BusinessDate.BASE_DATE to anything that can be understood as a business date, i.e. anything that meets businessdate.businessdate.BusinessDate.is_businessdate().

>>> BusinessDate.BASE_DATE = '20110314'
>>> BusinessDate()
BusinessDate(20110314)

>>> BusinessDate.BASE_DATE = None
>>> BusinessDate().to_date() == date.today()
True

Attention

Setting businessdate.businessdate.BusinessDate.BASE_DATE to +datetime.date.today()* is different to setting to None since +datetime.date.today()* changes at midnight!

BusinessPeriod

There are two different categories of periods which can’t be mixed.

One classical, given by a number of years, month, and days.

The second is business days or also known as working days, which are neither weekend days nor holidays. Holidays as seen as a container (e.g. list or tuple) of ` datetime.date which are understood as holidays.

Explicit keyword arguments of can be used to init an instance.

>>> BusinessPeriod()
BusinessPeriod('0D')

>>> BusinessPeriod(businessdays=10)
BusinessPeriod('10B')

>>> BusinessPeriod(years=2, months=6, days=1)
BusinessPeriod('2Y6M1D')

>>> BusinessPeriod(months=18)
BusinessPeriod('1Y6M')

>>> BusinessPeriod(years=1, months=6)
BusinessPeriod('1Y6M')

As seen month greater than 12 will be reduced to less or equal to 12 month with according years.

>>> BusinessPeriod(months=18)
BusinessPeriod('1Y6M')

>>> BusinessPeriod(years=2, months=6, days=1)
BusinessPeriod('2Y6M1D')

But this cannot be performed for days.

>>> BusinessPeriod(months=1, days=45)
BusinessPeriod('1M45D')

>>> BusinessPeriod(months=2, days=14)
BusinessPeriod('2M14D')

>>> BusinessPeriod(months=2, days=15)
BusinessPeriod('2M15D')

Caution

As mentioned, classical period input arguments years, month and days must not be combined with businessdays.

>>> BusinessPeriod(businessdays=1, days=1)
Traceback (most recent call last):
  File "<stdin>", line 1, in <module>
  File "/Users/jph/Dropbox/Apps/GitHub/sonntagsgesicht/businessdate/businessdate/businessperiod.py", line 103, in __init__
    raise ValueError("Either (years,months,days) or businessdays must be zero for %s" % self.__class__.__name__)
ValueError: Either (years,months,days) or businessdays must be zero for BusinessPeriod

Moreover, the difference of two instances of datetime.date*+ or resp. a **datetime.timedelta instance can be used to init, too.

>>> june_the_first, december_the_thirty_first = date(2010,6,1), date(2010,12,31)
>>> december_the_thirty_first-june_the_first
datetime.timedelta(days=213)

>>> BusinessPeriod(december_the_thirty_first-june_the_first)
BusinessPeriod('213D')

>>> timedelta(213)
datetime.timedelta(days=213)

>>> BusinessPeriod(timedelta(213))
BusinessPeriod('213D')

Similar to businessdate.businessdate.BusinessDate convenient string input work as well. Such a string represents again either periods of business days or classical periods.

>>> BusinessPeriod('0b')
BusinessPeriod('0D')

>>> BusinessPeriod('10D')
BusinessPeriod('10D')

>>> BusinessPeriod('1y3m4d')
BusinessPeriod('1Y3M4D')

>>> BusinessPeriod('18M')
BusinessPeriod('1Y6M')

>>> BusinessPeriod('1Q')
BusinessPeriod('3M')

>>> BusinessPeriod('2w')
BusinessPeriod('14D')

>>> BusinessPeriod('10B')
BusinessPeriod('10B')

Inputs like 1Q and 2W work, too. Here Q stands for quarters, i.e. 3 months, and W for weeks, i.e. 7 days.

As a convention in financial markets these three additional shortcuts ON for over night, TN tomorrow next and DD double days exist.

>>> BusinessPeriod('ON')
BusinessPeriod('1B')

>>> BusinessPeriod('TN')
BusinessPeriod('2B')

>>> BusinessPeriod('DD')
BusinessPeriod('3B')

The businessdate.businessperiod.BusinessPeriod constructor understands even negative inputs. Please note the behavior of the preceding sign!

>>> BusinessPeriod('-0b')
BusinessPeriod('0D')

>>> BusinessPeriod('-10D')
BusinessPeriod('-10D')

>>> BusinessPeriod('-1y3m4d')
BusinessPeriod('-1Y3M4D')

>>> BusinessPeriod('-18M')
BusinessPeriod('-1Y6M')

>>> BusinessPeriod('-1Q')
BusinessPeriod('-3M')

>>> BusinessPeriod('-2w')
BusinessPeriod('-14D')

>>> BusinessPeriod('-10B')
BusinessPeriod('-10B')

>>> BusinessPeriod(years=-2, months=-6, days=-1)
BusinessPeriod('-2Y6M1D')

Caution

Beware of the fact that all non zero attributes must meet the same sign.

>>> BusinessPeriod(months=1, days=-1)
Traceback (most recent call last):
  File "<stdin>", line 1, in <module>
  File "/Users/jph/Dropbox/Apps/GitHub/sonntagsgesicht/businessdate/businessdate/businessperiod.py", line 106, in __init__
    "(years, months, days)=%s must have equal sign for %s" % (str(ymd), self.__class__.__name__))
ValueError: (years, months, days)=(0, 1, -1) must have equal sign for BusinessPeriod
>>>

BusinessRange

Since BusinessRange just builds a periodical list of items like a range statement, it meets a similar signature and defaults.

>>> BusinessDate()
BusinessDate(20151225)

>>> start = BusinessDate(20151231)
>>> end = BusinessDate(20181231)
>>> rolling = BusinessDate(20151121)

>>> BusinessRange(start)
[BusinessDate(20151225), BusinessDate(20151226), BusinessDate(20151227), BusinessDate(20151228), BusinessDate(20151229), BusinessDate(20151230)]

>>> BusinessRange(start) == BusinessRange(BusinessDate(), start, '1d', start)
True

>>> len(BusinessRange(start))
6

>>> len(BusinessRange(start)) == start.diff_in_days(end)
False

>>> BusinessDate() in BusinessRange(start)
True

>>> start not in BusinessRange(start)
True

To understand the rolling, think of periodical date pattern (like a wave) expanding from rolling date to future an past. Start and end date set boundaries such that all dates between them are in the business range.

If the start date meets those date, it is included. But the end date will never be included.

>>> start in BusinessRange(start, end, '1y', end)
True

>>> end in BusinessRange(start, end, '1y', end)
False

>>> BusinessRange(start, end, '1y', end)
[BusinessDate(20151231), BusinessDate(20161231), BusinessDate(20171231)]

If the start date does not meet any date in the range, it is not included.

>>> start in BusinessRange(start, end, '1y', rolling)
False

>>> end in BusinessRange(start, end, '1y', rolling)
False

>>> BusinessRange(start, end, '1y', rolling)
[BusinessDate(20161121), BusinessDate(20171121), BusinessDate(20181121)]

Rolling on the same start and end but different rolling may lead to different ranges.

>>> start = BusinessDate(20150129)
>>> end = BusinessDate(20150602)
>>> rolling_on_start = BusinessRange(start, end, '1m1d', start)
>>> rolling_on_end = BusinessRange(start, end, '1m1d', end)

>>> rolling_on_start == rolling_on_end
False

>>> rolling_on_start
[BusinessDate(20150129), BusinessDate(20150301), BusinessDate(20150331), BusinessDate(20150502)]

>>> rolling_on_end
[BusinessDate(20150129), BusinessDate(20150227), BusinessDate(20150331), BusinessDate(20150501)]

Luckily, straight periods, e.g.

  • annually,

  • semi-annually,

  • quarterly,

  • monthly,

  • weekly or

  • daily,

don’t mix-up in such a way.

>>> start = BusinessDate(20200202)
>>> end = start + BusinessPeriod('1y') * 10
>>> BusinessRange(start, end, '1y', start) == BusinessRange(start, end, '1y', end)
True

>>> end = start + BusinessPeriod('6m') * 10
>>> BusinessRange(start, end, '6m', start) == BusinessRange(start, end, '6m', end)
True

>>> end = start + BusinessPeriod('1q') * 10
>>> BusinessRange(start, end, '1q', start) == BusinessRange(start, end, '1q', end)
True

>>> end = start + BusinessPeriod('1m') * 10
>>> BusinessRange(start, end, '1m', start) == BusinessRange(start, end, '1m', end)
True

>>> end = start + BusinessPeriod('1w') * 10
>>> BusinessRange(start, end, '1w', start) == BusinessRange(start, end, '1w', end)
True

>>> end = start + BusinessPeriod('1d') * 10
>>> BusinessRange(start, end, '1d', start) == BusinessRange(start, end, '1d', end)
True

BusinessSchedule

A businessdate.businessschedule.BusinessSchedule, as inhereted from businessdate.businessrange.BusinessRange, provides nearly the same features as businessdate.businessrange.BusinessRange. But businessdate.businessschedule.BusinessSchedule lists contain always start date and end date!

Since the first as well as the last period can be very short (short stubs), they can be trimmed to give a first and/or last period as long stubs.

>>> start = BusinessDate(20151231)
>>> end = BusinessDate(20181231)
>>> rolling = BusinessDate(20151121)

>>> BusinessRange(start, end, '1y', rolling)
[BusinessDate(20161121), BusinessDate(20171121), BusinessDate(20181121)]

>>> BusinessSchedule(start, end, '1y', rolling)
[BusinessDate(20151231), BusinessDate(20161121), BusinessDate(20171121), BusinessDate(20181121), BusinessDate(20181231)]

>>> BusinessSchedule(start, end, '1y', rolling).first_stub_long()
[BusinessDate(20151231), BusinessDate(20171121), BusinessDate(20181121), BusinessDate(20181231)]

>>> BusinessSchedule(start, end, '1y', rolling).last_stub_long()
[BusinessDate(20151231), BusinessDate(20161121), BusinessDate(20171121), BusinessDate(20181231)]

>>> BusinessSchedule(start, end, '1y', rolling).first_stub_long().last_stub_long()
[BusinessDate(20151231), BusinessDate(20171121), BusinessDate(20181231)]

BusinessHolidays

Since we deal with businessdate.businessdate.BusinessDate the container class businessdate.businessholidays.BusinessHolidays is useful as it converts nearly anything input into datetime.date.

Provide list of datetime.date or anything having attributes year, month and days, e.g. iterable that yields of businessdate.businessdate.BusinessDate.

For example you can use projects like python-holidays or workcalendar which offer holidays in many different countries, regions and calendars.

Build-in are businessdate.businessholidays.TargetHolidays which are bank holidays in euro banking system TARGET.

They serve as default value if no holidays are given. They can be changed on demand via the class attribute DEFAULT_HOLIDAYS in businessdate.businessdate.BusinessDate.

>>> BusinessDate(20100101) in BusinessDate.DEFAULT_HOLIDAYS
True

>>> BusinessDate.DEFAULT_HOLIDAYS = list()
>>> BusinessDate(20100101) in BusinessDate.DEFAULT_HOLIDAYS
False

Calculating Dates and Periods

Attention

Even adding and subtracting Dates and Periods suggest to be a kind of algebraic operation like adding and subtracting numbers. But they are not, at least not in a similar way!

Algebraic operations of numbers are known to be

  • compatible, e.g. 3 + 3 = 2 * 3 = 2 + 2 + 2

  • associative, e.g. (1 + 2) + 3 = 1 + (2 + 3)

  • distributive, e.g. (1 + 1) * 2 = 2 + 2

  • commutative, e.g. 1 + 2 = 2 + 1

Due to different many days in different months as well as leap years periods do not act that way on dates.

Note

For example, add 2 month to March, 31th should give May, 31th. But adding 2 times 1 month will give May, 30th, since

March, 31th + 1 month = April, 30th

April, 30th + 1 month = May, 30th

Even more pitfalls exist when izt comes to calculate dates and calendars. Fortunately periods acting on them self behave much more like numbers.

All this is build into businessdate.businessperiod.BusinessPeriod and businessdate.businessdate.BusinessDate.

Adding

Date + Period

Adding two dates does not any sense. So we can only add a period to a date to give a new date

>>> BusinessDate(20150612) + BusinessPeriod('6M19D')
BusinessDate(20151231)

Period + Period

And two periods to give a new period - as long as the do not mix business days and classical periods.

>>> BusinessPeriod('6M10D') + BusinessPeriod('9D')
BusinessPeriod('6M19D')

>>> BusinessPeriod('9D') + BusinessPeriod('6M10D')
BusinessPeriod('6M19D')

>>> BusinessPeriod('5B') + BusinessPeriod('10B')
BusinessPeriod('15B')

Subtracting

Date - Date

Surprisingly, the difference of two dates makes sense, as the distance in numeber of years than months and finaly days from the early to the later date.

>>> BusinessDate(20151231) - BusinessDate(20150612)
BusinessPeriod('6M19D')

Those are just the inverse operations

>>> period = BusinessDate(20151231) - BusinessDate(20150612)
>>> BusinessDate(20151231) == BusinessDate(20150612) + period
True

But note that these operations are not commutative, i.e. swapping the order can give something completely different as the the direction of the point of view is changed.

>>> dec31 = BusinessDate(20151231)
>>> jun12 = BusinessDate(20150612)

>>> dec31 - jun12  # it takes 6 months and 19 days from jun12 to dec31
BusinessPeriod('6M19D')

>>> jun12 - dec31  # jun12 is 6 months and 18 days before dec31
BusinessPeriod('-6M18D')

>>> jan29 = BusinessDate(20150129)
>>> mar01 = BusinessDate(20150301)

>>> mar01 - jan29  # from jan29 yoe waits 1 month and 1 day until mar01
BusinessPeriod('1M1D')

>>> jan29 - mar01  # but mar01 was 1 month and 3 days before
BusinessPeriod('-1M3D')

This becomes clear if you check this with your calendar.

diagram of jan29 + 1m1d = mar01 vs mar01 - 1m3d = jan29 (period algebra)

But still we get

>>> BusinessDate(20150612) - BusinessDate(20151231)
BusinessPeriod('-6M18D')

>>> BusinessDate(20150612) == BusinessDate(20151231) - BusinessPeriod('6M18D')
True

Date - Period

And again, we can subtract a period from a date to give a new date.

>>> BusinessDate(20151231) - BusinessPeriod('6M18D') == BusinessDate(20150612)
True

>>> BusinessDate(20151231) - BusinessPeriod('10b')
BusinessDate(20151216)

Period + Period

And straight forward, two periods substracted from each other to give a new period. Again, as long as the do not mix business days and classical periods.

>>> BusinessPeriod('6M19D') - BusinessPeriod('6M10D')
BusinessPeriod('9D')

>>> BusinessPeriod('-6M10D') - BusinessPeriod('-6M19D')
BusinessPeriod('9D')

>>> BusinessPeriod('10b') - BusinessPeriod('15b')
BusinessPeriod('-5B')

Multiplying

Period * int

Since an instance of a BusinessPeriod stored the number of years, month, days or businessdays as int one multiply this by integer, too.

Note that the number of month can be reduced if it’s exceeds the number of 12. But we can not do anything like this with days.

>>> BusinessPeriod('1y2m3d') * 2
BusinessPeriod('2Y4M6D')

>>> BusinessPeriod('1y8m200d') * 2
BusinessPeriod('3Y4M400D')

>>> y, m, d = 1, 2, 3
>>> BusinessPeriod(years=y, months=m, days=d) * 2 == BusinessPeriod(years=y*2, months=m*2, days=d*2)
True

>>> BusinessPeriod('1y2m3d') * 2 == 2 * BusinessPeriod('1y2m3d')
True

Comparing

Dates

Calendars assume time to be evolving in strictly one direction, from past to future. Hence days can be well ordered and so be compared. Same for BusinessDate.

>>> BusinessDate(20151231) < BusinessDate(20160101)
True

>>> BusinessDate(20151231) == BusinessDate(20160101)
False

>>> BusinessDate(20151231) > BusinessDate(20160101)
False

Periods

Two Tuples of three numbers (a,b,c) and (d,e,f) have only a natural order if all three numbers meet the same relation, e.g.

(a,b,c) < (d,e,f) if a < d and b < e and c < f

(a,b,c) == (d,e,f) if a == d and b == e and c == f

In case of a two classical period as a (years, months, days) the problem can be reduced by comparing only two numbers (years*12 + months, days).

But leveraging the order of dates, a period p can be seen as greater than a period q if for any possible date d adding both periods give always the same resulting order in dates.

I.e. we get

p < q if d + p < d + q for all dates d

Hence, we are left with only few situations, which might give for different dates d and d’

d + p < d + q but d’ + p >= d’ + q

Since days vary in different month, periods close to each other are difficult to compare, e.g. is 1M1D greater or equal 31D?

>>> p = BusinessPeriod('1M1D')
>>> q = BusinessPeriod('31D')

>>> BusinessDate(20150131) + p < BusinessDate(20150131) + q
True

>>> BusinessDate(20150731) + p < BusinessDate(20150731) + q
False

So, let (a,b,c) and (d,e,f) be two periods with

m = (a - b) * 12 + b - e and d = c - f

as the distance of both measured in months and days.

The sequence of the number of days in a period of given months with minimal days as well as max can be derived. The first 13 months listed.

months

num days

1

28 … 31

2

59 … 62

3

89 … 92

4

120 … 123

5

150 … 153

6

181 … 184

7

212 … 215

8

242 … 245

9

273 … 276

10

303 … 306

11

334 … 337

12

365 … 366

13

393 … 397

For those pairs of month and days any comparison of < or > is not well defined. Hence,

>>> BusinessPeriod('13m') < BusinessPeriod('392d')
False

>>> BusinessPeriod('13m') < BusinessPeriod('393d') # not well defined -> None

>>> BusinessPeriod('13m') < BusinessPeriod('397d') # not well defined -> None

>>> BusinessPeriod('13m') < BusinessPeriod('398d')
True

But

>>> BusinessPeriod('13m') <= BusinessPeriod('392d')
False

>>> BusinessPeriod('13m') <= BusinessPeriod('393d') # not well defined -> None

>>> BusinessPeriod('13m') <= BusinessPeriod('397d')
True

>>> BusinessPeriod('13m') <= BusinessPeriod('398d')
True

So comparison of arbitrary instances or BusinessPeriod only works for ==.

>>> BusinessPeriod('ON') == BusinessPeriod('1B')
True

>>> BusinessPeriod('7D') == BusinessPeriod('1W')
True

>>> BusinessPeriod('30D') == BusinessPeriod('1M')
False

>>> BusinessPeriod('1D') == BusinessPeriod('1B')
False

Adjusting

Dates

When adding a period to a date results on a weekend day may make no sense in terms of business date. This happens frequently when a interst payment plan is rolled out. In such a case all dates which fall either on weekend days or on holidays have to be moved (adjusted) to a business day.

In financial markets different conventions of business day adjustments are kown. Most of them are part of the ISDA Definitions which are not open to public. But see date rolling for more details.

>>> weekend_day = BusinessDate(20141129)
>>> weekend_day.weekday()  # Monday is 0 and Sunday is 6
5

>>> weekend_day.adjust('follow')  # move to next business day
BusinessDate(20141201)

>>> weekend_day.adjust('previous')  # move to previous business day
BusinessDate(20141128)

>>> weekend_day.adjust('mod_follow')  # move to next business day in same month else pervious
BusinessDate(20141128)

>>> BusinessDate(20141122).adjust('mod_follow')  # move to next business day in same month else pervious
BusinessDate(20141124)

>>> weekend_day.adjust('mod_previous')  # move to previous business day in same month else follow
BusinessDate(20141128)

>>> weekend_day.adjust('start_of_month')  # move to first business day in month
BusinessDate(20141103)

>>> weekend_day.adjust('end_of_month')  # move to last business day in month
BusinessDate(20141128)

In order to provide specific holidays a list of datetime.date objects can be given as an extra argument. It can convenient to use a businessdate.businessholidays.BusinessHolidays instance instead but any type that implements __contain__ will work.

>>> weekend_day.adjust('follow', holidays=[BusinessDate(20141201)])  # move to next business day
BusinessDate(20141202)

If no holidays are given the DEFAULT_HOLIDAYS of businessdate.businessdate.BusinessDate are used. By default those are the TARGET holidays.

To view all possible convention key words see businessdate.businessdate.BusinessDate.adjust() documentation.

Beside businessdate.businessdate.BusinessDate there is also businessdate.businessrange.BusinessRange.adjust() (same for businessdate.businessschedule.BusinessSchedule) which adjust all items in the businessdate.businessrange.BusinessRange.

>>> start = BusinessDate(20151231)
>>> BusinessRange(start)
[BusinessDate(20151225), BusinessDate(20151226), BusinessDate(20151227), BusinessDate(20151228), BusinessDate(20151229), BusinessDate(20151230)]

>>> BusinessRange(start).adjust('mod_follow')
[BusinessDate(20151228), BusinessDate(20151228), BusinessDate(20151228), BusinessDate(20151228), BusinessDate(20151229), BusinessDate(20151230)]

Measuring

Periods

Interest rates are agree and settled as annual rate. In contrast to this annual definition, interest payments are often semi-annually, quarterly or monthly or even daily.

In order to calculate an less than annal interest payment from an annual interest rate the year fraction of each particular period is used as

interest payment = annual interest rate * year fraction * notional

The year fraction depends on the days between the start date and end date of a period. In order to simplify calculation in the past there various financial markets convention to count days between dates, see detail on day count conventions.

The most common day count conventions, i.e. year fraction, are available by businessdate.businessdate.BusinessDate.get_day_count() and businessdate.businessdate.BusinessDate.get_year_fraction() (different name but same fuctionality).

To view all possible convention see businessdate.businessdate.BusinessDate.get_day_count() documentation.

>>> start_date = BusinessDate(20190829)
>>> end_date = start_date + '3M'

>>> start_date.get_day_count(end_date, 'act_act')
0.25205479452054796

>>> start_date.get_day_count(end_date, 'act_36525')
0.2518822724161533

>>> start_date.get_day_count(end_date, 'act_365')
0.25205479452054796

>>> start_date.get_day_count(end_date, 'act_360')
0.25555555555555554

>>> start_date.get_day_count(end_date, '30_360')
0.25

>>> start_date.get_day_count(end_date, '30E_360')
0.25

>>> start_date.get_day_count(end_date, '30E_360_I')
0.25

BusinessDate Details

More Creation Patterns

More complex creation pattern work, too. They combine the creation of a date plus a period with business day adjustemnt conventions at start and/or end of the period.

Create an instance directly from a period or period string.

>>> BusinessDate()
BusinessDate(20161009)

>>> BusinessDate() + '1m'
BusinessDate(20161109)

>>> BusinessDate(BusinessPeriod(months=1))
BusinessDate(20161109)

>>> BusinessDate('1m')
BusinessDate(20161109)

>>> BusinessDate('15b')
BusinessDate(20161028)

>>> BusinessDate() + '15b'
BusinessDate(20161028)

This works with additional date, too.

>>> BusinessDate('1m20161213')
BusinessDate(20170113)

>>> BusinessDate('20161213') + '1m'
BusinessDate(20170113)

Adding the adjustment convention ‘end_of_month’ with a business date gives the following.

>>> BusinessDate('0bEOM')
BusinessDate(20161031)

>>> BusinessDate('EOM')
BusinessDate(20161031)

>>> BusinessDate().adjust('EOM')
BusinessDate(20161031)

>>> BusinessDate('15bEOM')
BusinessDate(20161121)

>>> BusinessDate().adjust('EOM') + '15b'
BusinessDate(20161121)

Adding the adjustment convention ‘mod_follow’ with a business date lead to this.

>>> BusinessDate('0bModFlw')
BusinessDate(20161010)

>>> BusinessDate('ModFlw')
BusinessDate(20161010)

>>> BusinessDate().adjust('ModFlw')
BusinessDate(20161010)

>>> BusinessDate('15bModFlw')
BusinessDate(20161031)

>>> BusinessDate().adjust('ModFlw') + '15b'
BusinessDate(20161031)

But a adjustment convention with a classical period and without a business date is ignored since the adjustment statement is ambiguous:

Should the start date (spot) or end date be adjusted?

>>> BusinessDate('1mEOM')
BusinessDate(20161109)

>>> BusinessDate('1mModFlw')
BusinessDate(20161109)

Adding zero business days clarifies it!

>>> BusinessDate('0b1mModFlw')
BusinessDate(20161110)

>>> BusinessDate('0b1mModFlw') == BusinessDate().adjust('ModFlw') + '1m'
True

>>> BusinessDate('1m0bModFlw')
BusinessDate(20161109)

>>> BusinessDate('1m0bModFlw') == (BusinessDate() + '1m').adjust('ModFlw')
True

Clearly business days may be non zero, too.

>>> BusinessDate('15b1mModFlw')
BusinessDate(20161130)

>>> BusinessDate('15b1mModFlw') == BusinessDate('ModFlw') + '15b' + '1m'
True

>>> BusinessDate('1m5bModFlw')
BusinessDate(20161116)

>>> BusinessDate('1m5bModFlw') == BusinessDate('1m').adjust('ModFlw') + '5b'
True

Putting all together we get.

>>> BusinessDate('15b1m5bModFlw20161213')
BusinessDate(20170213)

>>> bd = BusinessDate(20161213)
>>> bd = bd.adjust('ModFlw')
>>> bd = bd + '15b'
>>> bd = bd + '1m'
>>> bd = bd.adjust('ModFlw')
>>> bd = bd + '5b'
>>> bd
BusinessDate(20170213)

>>> BusinessDate('15b1m5bModFlw20161213') == (BusinessDate(20161213).adjust('ModFlw') + '15b' + '1m').adjust('ModFlw') + '5b'
True

BusinessDate Inheritance

Finally some lines on base classes businessdate.basedate.BaseDateFloat backed by float

>>> from datetime import date
>>> from businessdate.basedate import BaseDateFloat

>>> BaseDateFloat(40123.)
40123.0

>>> BaseDateFloat.from_ymd(2009, 11, 6)
40123.0

>>> BaseDateFloat.from_date(date(2009, 11, 6))
40123.0

>>> BaseDateFloat.from_float(40123.)
40123.0

>>> d = BaseDateFloat(40123.)
>>> d.year, d.month, d.day
(2009, 11, 6)

>>> d.to_ymd()
(2009, 11, 6)

>>> d.to_date()
datetime.date(2009, 11, 6)

>>> d.to_float()
40123.0

… and businessdate.basedate.BaseDateDatetimeDate backed by datetime.date.

>>> from datetime import date
>>> from businessdate.basedate import BaseDateDatetimeDate

>>> BaseDateDatetimeDate(2009, 11, 6)
BaseDateDatetimeDate(2009, 11, 6)

>>> BaseDateDatetimeDate.from_ymd(2009, 11, 6)
BaseDateDatetimeDate(2009, 11, 6)

>>> BaseDateDatetimeDate.from_date(date(2009, 11, 6))
BaseDateDatetimeDate(2009, 11, 6)

>>> BaseDateDatetimeDate.from_float(40123.)
BaseDateDatetimeDate(2009, 11, 6)

>>> BaseDateDatetimeDate(2009, 11, 6)
BaseDateDatetimeDate(2009, 11, 6)

>>> d.year, d.month, d.day
(2009, 11, 6)

>>> d.to_ymd()
(2009, 11, 6)

>>> d.to_date()
datetime.date(2009, 11, 6)

>>> d.to_float()